Engineering

Major Bridge Scour Failures and What They Teach

Mike Jones 8 min read
On this page

FHWA’s HEC-18, Evaluating Scour at Bridges (fifth edition, 2012) opens its background section plainly: “The most common cause of bridge failures is from floods scouring bed material from around bridge foundations.” It then lists the toll: 73 bridges destroyed by floods in Pennsylvania, Virginia and West Virginia in 1985, and 17 bridges damaged or destroyed by scour in New York and New England in the spring floods of 1987.

This article is not about how armor fails physically. That is covered in why scour protection fails (winnowing, edge failure, undermining) and what failure actually looks like (what an inspector sees). This is about the failures that made it into official reports, and what the investigators concluded. Read together, they point less at hydraulics and more at maintenance, inspection and institutional memory.

We have kept to cases with a published investigation or an FHWA account. Where a number appears, it comes from that source.

1. Schoharie Creek Bridge, New York, 1987

What happened. On April 5, 1987, two spans of the New York State Thruway (I-90) bridge over Schoharie Creek fell about 80 feet into the flooded creek, killing 10 people. The NTSB investigation (HAR-88/02) found the probable cause was “the failure of the New York State Thruway Authority to maintain adequate riprap around the bridge piers, which led to severe erosion in the soil beneath the spread footings.”

The detail that matters. HEC-18 records that the bridge had survived a larger flood in 1955 (73,600 cfs) than the one that brought it down (62,100 cfs). Between those years, repeated floods removed the riprap. A 1979 consultant inspection found most of the riprap around the piers missing; the 1986 inspection did not detect a problem. The footings were spread footings with no piles, their tops at the streambed.

The lesson. Riprap is a maintenance item, not a permanent feature. HEC-18 draws the conclusion directly: inspectors “must recognize that riprap does not necessarily make a bridge safe from scour,” and must be trained to recognize when it is missing. Following the collapse, FHWA issued Technical Advisory T 5140.20 in 1988, establishing the national scour evaluation program that produced today’s scour critical ratings. See scour critical: what the rating means.

2. Hatchie River Bridge, Tennessee, 1989

What happened. On April 1, 1989, three spans of the northbound US 51 bridge over the Hatchie River collapsed, killing eight people. The NTSB (HAR-90/01) gave the probable cause as “the northward migration of the main river channel which the Tennessee Department of Transportation failed to evaluate and correct,” with lack of span redundancy contributing to the severity.

The detail that matters. The 1936 bridge crossed the floodplain on timber-pile bents. In 1974 a second, shorter southbound bridge was built, and its earthfill approaches blocked floodplain flow that used to pass through the old bridge’s open bents. HEC-18 describes how this concentrated the flow and pushed the channel north into the floodplain bents. Inspections in 1979, 1985 and 1987 accurately identified the migration, but the channel profile was not being plotted over time, inspectors did not have as-built plans, and they underestimated pile exposure (1 foot estimated, 3 feet actual). The flow at collapse, 8,620 cfs, was not large. A USGS study of the channel evolution followed.

The lesson. Channels move, and a new structure nearby can make them move. Successive cross sections need to be plotted and compared, inspectors need design or as-built plans on site, and a documented change needs someone whose job is to act on it. Lateral migration is a separate problem from local scour, and the two combined here.

3. Arroyo Pasajero (I-5), California, 1995

What happened. On March 10, 1995, the two I-5 bridges over Los Gatos Creek (Arroyo Pasajero) near Coalinga collapsed, killing seven people. Caltrans did not publish a report; HEC-18 summarizes the investigation by FHWA, USGS and consultant engineers, published by ASCE (Richardson et al. 1997).

The detail that matters. HEC-18 lists the factors: about 10 feet of long-term degradation since construction, a steeper channel from regional land subsidence, a drainage area increased by about a third when a channel was built linking Chino Creek to Los Gatos Creek, and severe contraction from a 300 to 400 foot channel to a 122 foot bridge. After a 1969 flood damaged a column, maintenance crews added a web wall between the pier columns. With the flow at an angle of 15 to 26 degrees, that wall potentially increased local pier scour by a factor of 3.6 to 4.4. Scour exposed the columns below the depth where they had reinforcing steel.

The lesson. A repair can change the hydraulics it was meant to resist. Any change to a substructure in the water, including a well-intentioned one, needs a scour check. And long-term degradation, the slowest component, can quietly consume most of a foundation’s margin. See contraction, local, and degradation scour.

4. The 1993 Upper Mississippi flood

What happened. HEC-18, citing Transportation Research Board Report 417, records 23 bridge failures in the 1993 upper Mississippi basin flood, with estimated damage of $15 million.

The detail that matters. The failure modes: 14 from abutment scour, two from pier scour, three from pier and abutment scour, two from lateral bank migration, one from debris load and one unknown.

The lesson. Piers get the attention; abutments fail. Most of the 1993 failures were at abutments, where floodplain flow turning around the embankment end concentrates attack. See abutment scour.

5. Tropical Storm Alberto, Georgia, 1994

What happened. HEC-18 reports that the 1994 flooding from Alberto damaged more than 500 state and locally owned bridges through scour. Thirty-one state-owned bridges saw 15 to 20 feet of contraction scour and/or long-term degradation on top of local scour and had to be replaced. Total damage to the Georgia DOT highway system was about $130 million.

The lesson. A single regional event can put hundreds of structures at risk at once, far more than an agency can inspect in the first days. Which bridges get looked at first, and what gets placed at them, has to be decided before the storm. The emergency scour response list and post-flood scour inspection cover that planning.

6. Malahide Viaduct, Ireland, 2009

What happened. On August 21, 2009, a pier of the Malahide Viaduct on the Dublin to Belfast line collapsed into the Broadmeadow Estuary just after a passenger train crossed. The driver saw it begin, signals were set to danger, and nobody was hurt. The Railway Accident Investigation Unit report (R2010-004) found the immediate cause was “the undermining of the weir that surrounds and supports Pier 4 through the action of scouring.”

The detail that matters. The piers stood on a grouted rock armor weir whose profile was kept up by periodically discharging stone. That maintenance regime appears to have stopped in 1996. An independent inspection in 1997 found scour starting at Pier 4 and called the rock armor “too light for the job,” with no evident follow-up. A 2006 scour assessment did not rate the viaduct high risk, and an inspection three days before the collapse missed scour defects visible at the time. The report also cites a “loss of corporate memory” as staff who knew the history left.

The lesson. Protection that depends on periodic replenishment only works while someone remembers to replenish it. Maintenance regimes need to be written down and owned, not carried in people’s heads.

7. Lamington Viaduct, Scotland, 2015

What happened. On December 31, 2015, a passenger train crossed the Lamington viaduct on the West Coast Main Line at about 110 mph while its central river pier was partially undermined by scour from high flow the previous day. Track deformed under the train. Nobody was hurt, and the line was closed for over seven weeks for emergency stabilization. The RAIB report (22/2016) sets out the sequence.

The detail that matters. The viaduct had been identified as high scour risk in 2005: shallow foundations on a river bend. A permanent scour protection scheme was due for 2015 but was deferred to mid-2016 because a necessary environmental approval had not been obtained. The interim control, monitoring river levels and closing the line above a set level, “was no longer in use,” and RAIB found no effective scour risk mitigation for over 100 of the most vulnerable structures across Scotland. There was also no datum level marked on the structure, so surveys from different sources could not be compared.

The lesson. An interim plan is only a plan while it is running. When a permanent fix is delayed, whether by funding or permitting, the monitoring and closure procedure covering the gap needs to be checked, not assumed. Permitting lead times belong in the risk plan. And a datum on the structure costs almost nothing.

What the seven have in common

Across these reports, the scour mechanism is rarely what surprised anyone. What recurs:

  1. Armor that was not maintained (Schoharie, Malahide). Placed protection was treated as permanent.
  2. Change that was recorded but not evaluated (Hatchie, Malahide, Lamington). Someone saw it; the system did not act on it.
  3. The river or the structure changed after design (Hatchie’s new bridge, Arroyo Pasajero’s web wall, subsidence and diversion). The original scour assessment no longer described the site.
  4. Abutments and contraction, not just piers (1993, 1994).
  5. Interim measures that lapsed while a permanent fix waited (Lamington).
  6. Lack of redundancy turning local damage into collapse (Schoharie, Hatchie).

Most of these are management failures, and most of the fixes are cheap compared with a collapse: as-built plans in the inspector’s hands, plotted cross sections, a datum on each pier, a written maintenance regime for any armor, and a live plan of action for every scour critical bridge. Reading a scour evaluation covers the assessment side.

When the answer is armor, choose it knowing it will need inspecting and topping up. The bridge scour protection products list compares the options against FHWA’s HEC-23 framework, and the scour monitoring technologies list covers the instruments that keep an interim plan honest.

FES Solutions is a supplier, not the engineer of record. This article is general engineering background, not a site-specific design. Conditions vary, and the design decision for your project belongs to the engineer of record. Where rock bags are not the right answer.

Written by
Mike Jones
Engineering Manager, FES Solutions

Mike Jones is Engineering Manager at FES Solutions. He holds a BS in civil engineering and an MS in hydrology, and spent 15 years with engineering firms and as an independent consultant on drainage and erosion control projects.