Most erosion and scour projects are delayed by authorization, not by material. Permitting, species consultation and floodway review routinely set the schedule while procurement waits, so establish the approval path before the layout is finalized rather than after.
This page sets out the federal framework for placing armor in US waters, what layers on top of it, and what a reviewer expects for a bagged armor solution. It follows the sequence a project moves through: which federal authority applies, whether a nationwide permit covers the work, what notification is required and when you may start, and what has to be kept for closeout.
Disclaimer — please read. This is general guidance, not legal advice and not a determination. The US Army Corps of Engineers district with jurisdiction makes the determination for your project, and district regional conditions, state certifications and local requirements vary substantially. Nothing here confirms that a particular installation is authorized under a particular permit. Confirm with the district, the state agency and the local authority having jurisdiction before work begins. Permit terms and dates cited are current as of publication.
The two federal authorities, and why both can apply
Placing armor in water in the United States engages one or two Department of the Army permit authorities, both administered by the Corps. They are separate authorities, not alternatives — this is the point most often gotten wrong.
Clean Water Act Section 404
Section 404, 33 U.S.C. 1344, implemented at 33 CFR Part 323, governs “the discharge of dredged or fill material into waters of the United States” — a reach broader than navigable waters, taking in many non-navigable tributaries and wetlands.
It triggers whenever riprap, rock bags, articulating concrete blocks, gabions, grout bags or any other fill material is discharged into a water of the United States. In practice, essentially all placed scour armor is a Section 404 discharge, and placing armor below the ordinary high water mark generally falls within it.
Rivers and Harbors Act Section 10
Section 10 of the Rivers and Harbors Act of 1899, 33 U.S.C. 403, implemented at 33 CFR Part 322, covers “certain structures or work in or affecting navigable waters of the United States.” Its trigger is narrower geographically — traditional navigable waters — but broader in kind, reaching work and structures rather than only discharges. It attaches to work at berths, in navigable rivers and in coastal waters. Navigability is a legal determination, not an obvious physical one, so confirm it early.
Both, together
Both implementing regulations expressly cross-reference each other: a Department of the Army permit will also be required under the additional authority if it is applicable. Projects in navigable waters frequently need both, reviewed together by the district. NWP 13 carries the authority line “(Authorities: Sections 10 and 404)” and authorizes discharges of dredged or fill material into waters of the United States or work and structures in navigable waters associated with bank stabilization — written to cover either or both.
Two related authorities should not be conflated with these: Rivers and Harbors Act Section 9 (33 U.S.C. 401; dams and dikes, 33 CFR Part 321) and MPRSA Section 103 (33 U.S.C. 1413; ocean disposal, 33 CFR Part 324).
The 2026 Nationwide Permits
What changed, and when
The nationwide permits were reissued in the Reissuance and Modification of Nationwide Permits, published in the Federal Register on 8 January 2026. There are 57 nationwide permits — 56 reissued and one new. They took effect on 15 March 2026 and expire on 15 March 2031. The 2021 nationwide permits expired on 14 March 2026. Any permitting narrative or checklist assembled from pre-2026 sources is out of date.
NWP 13 — Bank Stabilization
NWP 13 is the general permit most routine erosion repair runs through. It authorizes “bank stabilization activities necessary for erosion control or prevention, such as vegetative stabilization, bioengineering, sills, rip rap, revetment, gabion baskets, stream barbs, and bulkheads, or combinations of bank stabilization techniques,” provided the activity meets all nine of its criteria.
The scope sentence lists techniques by example — “such as” — rather than as a closed list, and rock bags are not among the named examples. That is a question for the district, not a disqualification, and one reason product documentation matters at the notification stage.
The nine criteria, condensed but accurate:
- (a) No material in excess of the minimum needed for erosion protection.
- (b) No more than 500 feet in length along the bank — waivable by written district engineer determination of no more than minimal adverse environmental effects, except that no waiver may be issued for a bulkhead greater than 1,000 feet in length along the bank.
- (c) Not to exceed an average of one cubic yard per running foot, measured along the treated bank, below the plane of the ordinary high water mark or high tide line — waivable by written determination.
- (d) No discharges into special aquatic sites — waivable by written determination.
- (e) No material of a type, location or manner that will impair surface water flow into or out of any waters of the United States.
- (f) No material placed in a manner that will be eroded by normal or expected high flows; properly anchored native trees and treetops are permitted in low energy areas.
- (g) Native plants appropriate for current site conditions, including salinity, for any bioengineering or vegetative stabilization.
- (h) Not a stream channelization activity.
- (i) Must be properly maintained, which may require repair after severe storms — and the NWP authorizes that repair.
Getting the thresholds right
NWP 13 has no acreage threshold. Its limits are linear — 500 feet along the bank — and volumetric — an average of one cubic yard per running foot below the ordinary high water mark or high tide line. Two corrections worth making explicitly: the volumetric limit is one cubic yard per running foot, not one-third of a cubic yard; and the 1/3-acre figure often attached to NWP 13 belongs to NWP 14 (Linear Transportation Projects), where the discharge cannot cause the loss of greater than 1/3-acre in tidal waters, or 1/2-acre in non-tidal waters.
Criteria (b), (c) and (d) are waivable by written determination of no more than minimal adverse environmental effects. Exceeding a threshold does not disqualify the work — but it compels a pre-construction notification and requires that determination.
Nature-based solutions, new in the 2026 NWP 13
The 2026 NWP 13 expressly authorizes incorporating nature-based solutions into new and existing bank stabilization — among them various sizes of rock in revetments to give different sizes of spaces between rocks for habitat, rock pools, pocket beaches, rock clusters, large wood, and placement of bags of molluscs or small reef structures. A new Note 2 encourages soft approaches where effective while acknowledging that hard stabilization may be necessary at sites subject to strong erosive forces, and lists factors to weigh: bank height and condition; energy of tides, waves and currents; fetch; nearshore depths; storm surge potential; sediment type; tidal range; shoreline configuration and orientation; waterway width; and the infrastructure needing protection. That list works as a checklist for the design narrative. Note 1 points to NWP 54 (Living Shorelines) in coastal waters and the Great Lakes.
NWP 3 — Maintenance
NWP 3(a) covers repair, rehabilitation or replacement of any previously authorized, currently serviceable structure or fill, provided it is not put to uses differing from those specified or contemplated in the original permit. Minor deviations in configuration or filled area are authorized, including those due to changes in materials, construction techniques, requirements of other regulatory agencies, or current codes or safety standards — the provision under which a replacement in a different material is normally considered. Storm, flood or fire damage repair is covered where work is commenced, or under contract to commence, within two years of the damage, waivable for catastrophic events.
NWP 3(b) covers removal of accumulated sediments and debris outside the immediate vicinity of existing structures such as bridges and water intakes, limited to the minimum necessary and not extending farther than 200 feet in any direction from the structure — a limit that does not apply to maintenance dredging of outfall and intake structures or their canals. A PCN is required only for paragraph (b) activities.
Other nationwide permits worth knowing here
NWP 14 Linear Transportation Projects · NWP 27 Aquatic Ecosystem Restoration, Enhancement, and Establishment Activities · NWP 31 Maintenance of Existing Flood Control Facilities · NWP 33 Temporary Construction, Access, and Dewatering · NWP 45 Repair of Uplands Damaged by Discrete Events · NWP 54 Living Shorelines. Which fits — and whether more than one is in play — is a district determination.
Pre-construction notification, and when you may actually start
What a PCN is
A pre-construction notification is a written notification to the Corps district engineer, submitted before starting work, letting the district engineer verify the activity qualifies for the nationwide permit and add special conditions. It is not an application for an individual permit, and not required for every NWP activity — only where the terms of the NWP require it. Requirements are in General Condition 32.
When NWP 13 requires one
A PCN is required if the activity involves discharges into special aquatic sites; or is in excess of 500 feet in length; or will involve discharge of greater than an average of one cubic yard per running foot as measured along the treated bank, below the plane of the ordinary high water mark or high tide line. Those are the same measures the district engineer may waive — so exceeding one compels a PCN rather than ending the inquiry.
The 30-day and 45-day clocks
Submit the PCN as early as possible. The district engineer must determine whether it is complete within 30 calendar days of receipt and, if incomplete, notify the applicant within that period to request additional information. As a general rule the district engineer requests additional information only once; if the applicant does not supply everything, the review process does not commence until all requested information has been received. That is the reason to over-prepare the first submission.
Work may not begin until either written notice from the district engineer that the activity may proceed with any special conditions, or 45 calendar days have passed from receipt of the complete PCN with no written notice received. The 45 days run from receipt of the complete PCN, not from the original submission.
The exception that catches people out
Where the permittee was required to notify the Corps under General Condition 18 (endangered species and designated critical habitat) or General Condition 20 (historic properties), the permittee cannot begin the activity until receiving written notification. The 45-day clock does not self-authorize in those cases. Treating silence as authorization on a project with a listed species or historic property issue is an unauthorized start.
What layers on top of the federal permit
The national NWP text is a floor, not the whole requirement.
Regional conditions
Districts and divisions issue regional conditions under General Condition 27. These can add PCN triggers, reduce thresholds below the national figures, or exclude certain waters entirely. Never state that an installation “is covered by NWP 13” without the district-specific check.
State Section 401 water quality certification
General Condition 25 carries the state water quality certification requirement. States can deny, condition or waive certification, and state conditions become conditions of the federal permit. This is frequently where turbidity limits, monitoring requirements and work-window restrictions actually originate.
Coastal Zone Management consistency
General Condition 26 covers Coastal Zone Management Act consistency: in coastal states the state coastal program reviews work in the coastal zone against the state program, in addition to federal authorization. Several states have shifted policy toward sloped, permeable protection and away from new vertical walls, which affects what a reviewer will accept before it affects what is feasible. See coastal protection.
Mitigation, and everyone else with jurisdiction
General Condition 23 requires compensatory mitigation for wetland losses greater than 1/10-acre and stream losses greater than 3/100-acre that require PCNs, at a minimum one-for-one ratio — unless the district engineer determines in writing either that some other form of mitigation would be more environmentally appropriate, or that the adverse environmental effects are no more than minimal, and provides an activity-specific waiver.
Beyond the Corps and the state water agency, the path may involve state fish and wildlife departments, coastal zone programs, local floodplain administrators, port authorities and municipal shoreline offices — plus tribal governments, NOAA Fisheries or the US Fish and Wildlife Service where protected species or federal consultation apply.
What a reviewer wants to see for a bagged armor solution
Reviewers generally look for three things:
- Independent material evidence. Properties validated by an independent laboratory, with the method and laboratory named for each, rather than a self-certified general product claim. That is the purpose of the test data page.
- A sizing rationale connected to site hydraulics. A stated design velocity and depth, where those numbers came from, and how the selected unit relates to them. The hydraulic design guide sets out that chain — including the part most often missed: federal countermeasure guidance provides no design guideline for rock-filled geotextile bags as an armor layer, so the sizing basis is FES’s own tested resistance data and should be presented as such rather than dressed up as conformance to a guideline that does not exist. Reviewers notice the difference.
- Layout drawings. Extent, depth, toe elevation, edge treatment and transitions, in plan and cross-section.
A Section 404 or Section 10 submittal may also need project purpose, location and coordinates, site photographs, ordinary high water or tidal boundaries, and the proposed quantity and area of fill; and may need to describe temporary and permanent impacts, construction access, placement methods, work dates, avoidance measures, alternatives considered and restoration. FES supplies product dimensions, materials and testing data for the rock bag portion; the applicant remains responsible for the complete package.
Two characteristics help on their own merits: the armor is permeable and colonizable rather than a sealed face, and it can be placed in flowing water without dewatering a reach — removing a cycle that is itself a significant turbidity source. Neither substitutes for the agency’s determination.
The permits around the federal permit
Construction stormwater and NPDES
Where the project disturbs enough ground to trigger it, construction stormwater permitting applies, typically through an NPDES construction general permit and a stormwater pollution prevention plan. Rock bags are permanent erosion control rather than a temporary construction best management practice, so they normally appear as the permanent stabilization measure while silt fence, wattles and inlet protection cover the construction phase. See stormwater and drainage.
Floodplain permitting and no-rise
Work in a regulated floodway generally requires the local floodplain administrator to be satisfied it does not increase base flood elevations. Armor occupying meaningful flow area affects that calculation, so section thickness and extent may be constrained by the no-rise analysis rather than by hydraulics alone. Establish that constraint before the layout is finalized — reworking it afterwards is expensive.
In-water work windows
Permit conditions frequently limit in-water construction to dates that avoid spawning, migration, incubation or juvenile rearing, and those windows are often the binding schedule constraint, ahead of procurement. A short window affects aggregate delivery, filling, mobilization, daily production targets and the sequence used to protect unfinished sections, so materials and staging should be ready before it opens. Flag the window in the quote request so lead time is planned against it.
Endangered species consultation
Where a listed species or designated critical habitat is present, federal authorization triggers consultation under Section 7 of the Endangered Species Act between the permitting agency and the relevant service. It commonly produces conditions on timing, methods and monitoring rather than a refusal. Identify it early — consultation is often the longest single item in a permitting schedule, and it is what triggers the General Condition 18 hold described above.
Turbidity controls and work-area isolation
Controls may include clean aggregate, stabilized access, controlled lowering, turbidity curtains, staged work, spill prevention and monitoring above and below the placement area — matched to current, depth, substrate and permit limits, since a curtain that works in still water may fail or redirect flow in a channel. A regulator may also require work-area isolation even though rock bags can be installed in flowing water, and that isolation must itself be designed so it does not create a new scour path, strand aquatic life or increase flooding upstream. Product capability does not override permit conditions written for the site. Note too that some permits specify washed aggregate to limit turbidity, and some restrict sources to avoid transporting invasive species between waterbodies.
Emergency authorizations, and their limits
Most jurisdictions have an emergency provision allowing protective work to proceed ahead of full authorization where there is an imminent threat to life, property or essential infrastructure. The provision is real, but narrow and jurisdiction-specific, and it does not create an exemption from permitting.
The practical sequence: contact the appropriate Corps district and state agencies before work begins; provide location, damage description, proposed repair, quantities, photographs and requested construction dates; then follow the direction received. Additional consultation, reporting, mitigation, restoration or removal conditions commonly follow once the hazard is controlled. Confirm the provision with the agency rather than assuming it applies. FES can coordinate rapid delivery for approved emergency work — see emergency response.
State DOT projects and a product not on a materials list
State DOT work adds a materials approval track alongside the environmental permits. Where a product is not on a standard materials list, the normal route is a submittal evidencing the properties the specification calls for, reviewed by the department. A departmental reviewer is checking properties against a specification, not evaluating a marketing document — which is why the FES test program names the method and the independent laboratory for each property. Assemble that evidence early; it removes a common source of review delay. See DOT and municipal work and the test data page.
Public infrastructure work, and most permitted work, also requires a professional engineer’s stamp from an engineer licensed in the state and engaged by the project rather than by the supplier. Product sizing guidance supports that engineer’s work; it does not substitute for it.
Where a project is funded through a watershed or conservation program run by a conservation district or a federal agriculture agency, that program’s design standards, cost-share rules and documentation requirements sit on top of the environmental permits rather than replacing them — and usually govern the design. Obtain it before sizing.
How long it takes
Realistically: from a few weeks under a nationwide permit with no complications, to well over a year where an individual permit, species consultation and a floodway analysis all apply. The planning assumption that holds up is that permitting, not product lead time, sets the schedule.
Two things compress it: submitting a complete PCN the first time — the district engineer generally requests additional information only once, and the clock does not start until everything is in — and having material documentation assembled before it is asked for.
Records to retain for closeout and compliance
Retain permits and approvals, final drawings, pre-construction notifications, aggregate documentation (quarry or source, material description, sieve analysis, delivery tickets and any certification the permit requires), filling records, daily reports, inspection forms, photographs, monitoring results and approved field changes. The file should also include wildlife observations, spill or turbidity reports, restoration work, material disposal records and the final as-built survey.
Where the permit or a restoration plan imposes habitat monitoring, it will identify locations, methods, frequency, performance criteria and the response required when a target is missed — commonly tracking bed and bank elevations, sediment accumulation, vegetation survival, aquatic colonization, turbidity and the stability of the installed units. Baseline photographs and surveys collected before construction are what make later comparisons meaningful.
Agencies may set a retention period or require copies with the closeout report. FES supplies test data and project documentation; the permit holder maintains the compliance record.
What to send us
For permitting support: project location and waterbody, the authorities and agencies already identified, whether a PCN is expected, the in-water work window if one applies, design velocity and depth, quantity and coverage area, and the submittal deadline.
Send it through the quote form, or call +1 512-766-6608 if the scope is on a short clock.