Why the bottom keeps washing out around your dock pilings

Mike Jones 7 min read
On this page

The lake bed near your dock used to be one level. Now there is a dish around each piling, the ladder does not reach the way it used to, and the gravel somebody dumped in last year is gone.

That is scour, and it is not the same thing as your bank eroding. It has a different cause, it happens in a different place, and — this is the part that costs people money — backfilling it does not fix it. The material you put in leaves the same way the original material did, usually faster, because loose fill moves more easily than the bed it replaced.

This page explains what is actually happening and what stops it. It is about the bed around your structure, not about the structure itself — that part belongs to your marine contractor.

What scour actually is

Put anything solid into moving water and the water has to go around it. Going around means accelerating, and accelerating water carries more material than slow water does.

So the fastest water in the area is right at the thing you installed, and the bed there is the first bed to leave. The hole that forms is deepest against the structure and shallows outward — which is why it looks like a dish rather than a trench, and why it appears at the pilings rather than between them.

Three things worth knowing about it:

  • It is self-reinforcing. A hole changes the flow, and the changed flow deepens the hole.
  • It happens in events, not gradually. Most of a season’s scour arrives during a handful of storms or high-flow days.
  • The same mechanism operates at every scale. It is the reason bridge piers and port berths need protection, and the engineering is identical — only the size changes. See bridge abutment scour protection and port berth scour and propeller wash if you want the larger version.

What is driving it at your dock

Usually more than one of these at once.

Waves and boat wake

Wave energy at the waterline moves material and the water rebounding off pilings and lift legs concentrates it. On a busy lake, wake is often the dominant cause and it arrives all summer.

Your own propellers

Propeller wash directs a concentrated jet of water at the bed. Manoeuvring into a slip, running up to trim, or holding position while somebody steps off puts that jet in the same place repeatedly — which is why the deepest hole is so often exactly where the boat sits, not where the current runs.

Current, if you are on a river

A river adds a steady directional component, and the scour pattern becomes lopsided — deeper on the upstream face, with a tail downstream.

Water level moving

As the level falls, water drains out of the bank and the bed near it, and material that was stable saturated becomes material that moves.

Whatever is next to it

A wall, a bulkhead, or a neighbouring structure reflects wave energy rather than absorbing it, and the reflected energy has to go somewhere. Frequently that somewhere is the bed at your pilings.

Why the gravel you added disappeared

Because loose material sized for a driveway is not sized for the condition that removed the last lot.

Whether a particle stays put is a relationship between its weight and the force of the water on it. Undersized material leaves. And it leaves faster than the original bed did, because a fresh dump of loose stone has no interlock and sits proud of the surrounding bed, where the flow is quickest.

The two ways to make material stay:

  1. Make each piece heavy enough that the design condition cannot move it — which at a residential dock often means stone considerably larger than people expect, with the access problem that implies.
  2. Group the material so the water has to move the whole assembly rather than a piece at a time. This is the principle behind bagged armor: the fill can be locally available rock, but the unit the water has to shift is the whole filled bag.

Both work. Which is appropriate depends on the condition, the access, and what is already in the water.

Does the scour threaten the structure?

This page cannot answer that, and neither can a supplier. It is a structural question about your specific dock — how deep the pilings go, what they bear on, and how much of their support the hole has removed. Your marine contractor or a structural engineer answers it, and it is worth asking rather than assuming.

What is worth knowing is the general shape of the concern: pilings get support from the material along their embedded length, and scour removes some of that. A shallow dish is usually cosmetic. A deep hole against a piling on a structure that was marginal to begin with is a different conversation. If the structure has moved, racked, or become noticeably less rigid, that conversation is overdue.

Protecting the bed does not repair a structure that has already lost support. Sequence matters: any structural remediation happens first, bed protection second, or you protect a bed under something that then has to be worked on again.

How the area gets stabilised

The aim is to armor the bed where the flow is fastest, extending far enough out that the edge of the protection sits in slower water than the material can withstand.

Coverage, not a plug

The most common mistake after backfilling is treating the hole as the problem and filling only the hole. The hole is the symptom. Protection has to extend beyond the accelerated zone in every direction, or the bed simply fails at the new edge and works inward.

The toe still matters

If your bank is also retreating, the toe of the bank and the bed at the structure are the same problem in two places, and treating them as one design costs less and works better than two separate visits. Bulkhead alternatives for a lakefront bank covers the bank side.

Working around what is already there

Existing structures are a design constraint, not an obstacle. Placement around pilings, lift legs, ladders and steps is routine, but it changes the sizes that fit and the equipment that can reach — so tell whoever is quoting exactly what is in the water before they price it, not after.

Size and equipment

Residential dock work normally sits at the smaller end of the range — the 1-Ton and 2-Ton classes — because the units have to fit between and around structures and because the equipment that can reach a private shoreline is limited. Size is set by the hydraulic condition rather than preference; the sizing guide covers how that is worked out.

Placement in the water

Bags are filled on site with locally sourced stone and placed with an excavator, and they can be placed into water rather than requiring the area to be dewatered — which matters at a dock, where dewatering is rarely practical.

A few things worth doing first

  • Photograph it, with a measure. A pole marked in feet, at the same spot, a few times a season. Scour is episodic, and a record tells you whether it is progressing or stable — which is genuinely the difference between acting now and monitoring.
  • Sound the depth around each piling and note where the deepest point is. It tells you which mechanism is dominant.
  • Notice when it gets worse. After storms points at waves. After busy weekends points at wake and prop wash. Steadily, on a river, points at current.
  • Ask your marine contractor about the structure before you spend anything on the bed.
  • Check the permit path. Work at and below the waterline is usually regulated, including around an existing dock. See do you need a permit to fix your shoreline.

What to send us

For sizing around a dock, pier or lift, the useful set is: photographs of the structure and the water around it, sounded depths at the pilings and away from them, the approximate area to be protected, normal and high water levels if known, what else is in the water (lift, ladder, steps, adjacent wall), how equipment can reach the shoreline, and any permit conditions already imposed.

Send it through the quote form, or call +1 512-766-6608. Sizing and pricing come back within one business day.

Related: Bulkhead alternatives for a lakefront bank · What shoreline erosion repair costs · Property owners & HOAs · Marine & ports · Do you need a permit? · When not to use rock bags · Full FAQ

FES Solutions is a supplier, not the engineer of record. This article is general engineering background, not a site-specific design. Conditions vary, and the design decision for your project belongs to the engineer of record. Where rock bags are not the right answer.

Written by
Mike Jones
Engineering Manager, FES Solutions

Mike Jones is Engineering Manager at FES Solutions. He holds a BS in civil engineering and an MS in hydrology, and spent 15 years with engineering firms and as an independent consultant on drainage and erosion control projects.