FES publishes a service life of approximately 100 years for the part of a rock bag that sits under water, backed by EN 12447 hydrolysis testing. For bags on land, the figure is 50 to 100 years, provided the bag is covered within a month of installation, backed by EN 12224 weathering and BS EN ISO 13438 oxidation testing. The 1-Ton uses the same raschel-weave virgin polyester as every size, so these figures apply to it. Bags left permanently bare in the sun fall outside the on-land assumption.
Why there are two numbers
Different things age the mesh in different places:
- Under water, the mesh is out of the sun. The slow process that matters is the effect of water on the polyester, which is what hydrolysis testing measures. This is the part of an installation least at risk.
- Above water, sunlight is the main thing that ages the mesh. That is what weathering testing measures. The published on-land figure assumes the bag is covered, by soil, planting, or sediment, within a month.
More detail: service life in water vs. on land and EN 12447 and EN 12224.
What this means on a residential bank
A typical 1-Ton job on a creek or pond has three zones:
| Zone | What ages the mesh | What to do |
|---|---|---|
| Below normal water level | Water, slowly | Nothing special. This is the longest-lasting part. |
| The waterline | Sun, wave action, ice, debris | Inspect after storms and each year |
| Above the waterline | Sun | Cover with soil and planting within a month |
The upper row of bags on a stepped bank is the one most likely to sit in the sun. Planning soil and planting over it is the simplest way to stay within the published figure. See planting over 1-ton rock bags.
What shortens life
- Permanent sun exposure on bags left bare above the water
- Wrong fill: stone smaller than the 25 mm mesh opening works out over time, and the bag thins. See how much fill stone you need.
- Rough handling: dragging filled bags across the ground, or dropping stone from height into them
- Ice and heavy debris at the waterline. See ice damage to bank protection.
- A bank that keeps moving because the real problem was never erosion. See when a 1-ton rock bag is not enough.
Virgin vs. recycled polymer
The mesh is virgin polyester, not recycled material. FES’s view of why that matters is in virgin vs. recycled polymer. When you compare suppliers, ask what each one’s service-life figure assumes and which test backs it.
What failure looks like, and what to do
Failure is usually local: one bag at the waterline that is cut, worn, or has lost fill. Because each bag is a separate unit, the fix is usually to lift that bag out and set a new one. See what failure actually looks like and inspecting and maintaining 1-ton rock bags.
For the full engineering version, see how long rock bags last, and how they fail. For the product, see the 1-Ton Rock Bag.