For a single row of 1-Ton Rock Bags, plan on about 23 to 24 bags per 100 feet of bank. That comes from FES’s own layout rule. Each bag is counted as covering 85 to 90 percent of its 1.5 m filled diameter along the bank, or about 4.2 to 4.4 feet. Then multiply by the number of rows the height of the bank needs.
This is a starting count for budgeting and for a quote request. It is not a bill of quantities. The final number comes from FES engineering once they see the site.
Rule 1: coverage along the bank
Round bags placed side by side do not cover their full width, because they meet at a curve. So FES counts each bag as covering 85 to 90 percent of its diameter.
For the 1-Ton:
| Metric | Feet | |
|---|---|---|
| Filled diameter | 1.5 m | about 4.9 ft |
| Effective coverage at 90% | 1.35 m | about 4.4 ft |
| Effective coverage at 85% | 1.275 m | about 4.2 ft |
Bags per row = length of bank ÷ effective coverage. Round up.
Rule 2: rows for height
If the protection has to go higher than one bag, add rows. Rows = height to protect ÷ settled bag height. A taller bank gets more rows, not a bigger bag.
The settled height of a filled 1-Ton depends on the fill and how it beds in. FES confirms it for your fill, so this page does not guess at a number. For a first budget, work out the one-row count, then ask how many rows your bank height needs.
Rule 3: the slope sets the shape
- A steep, near-vertical face is stacked straight up.
- A gentler slope is stepped back in a stair-step profile, with each row set back from the one below.
A stair-step layout covers more slope per row, so the bank’s angle changes the count as well as the look. See slope steepness and stacking and layouts: single, stacked, keyed.
A worked example
A pond bank is undercut along 60 feet. The owner wants one row of 1-Ton bags along the toe.
- 60 ft ÷ 4.4 ft = 13.6, so 14 bags
- 60 ft ÷ 4.2 ft = 14.3, so 15 bags
- Starting count: 14 to 15 bags for one row
If the design calls for a second row stepped back above the first, the count roughly doubles, give or take the ends.
What changes the real number
The rules above give a sound starting count. A real order also allows for:
- Running past the damage. Protection should start and end in ground that is not eroding, not at the edge of the visible damage. That adds bags at each end. See transitions and terminations.
- Tying into a dock, wall, or pipe. The joins need care, and sometimes extra units. See interfacing with existing structures.
- A toe set into the bed, below the current ground line, so the water cannot get under it.
- An existing scour hole that has to be filled before the line is built.
- Curves. A bank that bends takes a few more bags than a straight one of the same length.
FES’s sizing calculator shows the same rules next to the size check.
What to send for an exact count
- Length of bank to protect, in feet or meters
- Height from the toe (or the bed) to where the protection should stop
- Rough slope: near-vertical, steep, or gentle
- Photos from the water and from the top of the bank
- Any structures in the line: dock, steps, outfall, wall
- The machine that can reach the bank
Send it through the quote form. FES engineering will come back with a recommended size and quantity. See also what a quote includes.